Short answer
For a standard house with a tiled roof between 60 and 120 m², the work on the roof usually takes 3 to 5 working days. Including finishing and handover, an average project comes to 3 to 6 working days. Before that there is a preparation phase of 1 to 3 weeks on average for inspection, quote, scheduling and ordering materials.
How long does it take to replace a tiled roof? That is often the first question as soon as leaks, loose tiles or an ageing roof come into view. The duration determines not only the planning in and around your home, but also the cost, the disruption and the period during which your roof is temporarily less well protected. It is therefore wise to have realistic expectations about the lead time in advance.
In this article you can read what the duration of a tiled roof replacement depends on, which phases such a project involves and how much time each phase takes on average. You can also read how we limit the disruption for you and your neighbours and how cost, planning and timeline are related.
What does the duration of a tiled roof replacement depend on?

The most important factor is the surface area and shape of your roof. A simple straight pitched roof of 60 m² can usually be replaced considerably faster than a complex roof of 150 m² with several dormers, chimneys and corners. The more details, penetrations and differences in height, the more time the roofers need to finish everything watertight and neatly. The type of tile also plays a role: some ceramic, concrete or special models require more laying work than others.
In addition, the condition of the roof structure is crucial. Is only the roof covering due for replacement, or do the roof decking, the insulation or even the joists also need to be (partly) renewed? If the free roof inspection shows that the timber has been affected by moisture or wood rot, the structure must be repaired first. That can extend the project by one or more days, but prevents future problems and extra costs.
Accessibility and logistics also count. A house that is easily accessible for a ladder lift or crane, where materials can be stored and a skip can be placed, simply works faster. In a city centre with narrow streets, little parking space and strict rules for building sites, the planning has to be more precise and often set up with a bit more slack. We take this explicitly into account during preparation.
- Surface area and shape: a straight pitched roof is quicker than a roof with many corners and details.
- Type of tile: some models require more laying work.
- Condition of the structure: wood rot or moisture damage must be repaired first.
- Extras: insulation, new gutters or zinc work add working days.
- Accessibility: space for scaffolding, lift and skip saves time.
Average duration per phase of the roofing project
A professional roof replacement runs in three phases. The working days on the roof are only part of the total process.
| Phase | What happens | Average duration |
|---|---|---|
| Preparation | free roof inspection, quote, scheduling, ordering materials, permit or notification if needed | 1 – 3 weeks |
| Work on the roof | scaffolding, old tiles removed, substructure checked, membrane, battens, new tiles, details | 3 – 5 working days (60 – 120 m²) |
| Finishing and handover | roof checked, details finished, site cleared, handover inspection with you | 0.5 – 1 day |
Phase 1: preparation
This phase includes the free roof inspection, a clear quote, scheduling, ordering materials and, if necessary, arranging a permit or notification with the municipality. This largely happens out of your sight and takes 1 to 3 weeks on average, depending on the delivery time of the tiles and how busy the schedule is. Good preparation makes the time on site shorter and more predictable. Unsure about a permit? Then read whether you need a permit to replace roof tiles.
Phase 2: work on the roof
For a standard house with a tiled roof between 60 and 120 m², the lead time is usually about 3 to 5 working days. The first day(s) are devoted to the scaffolding, removing the old tiles, checking the substructure and applying or improving insulation and roofing membrane. Then the new battens are fitted, the tiles laid and details such as ridge tiles (nokvorsten), valley gutters (kilgoten), penetrations and dormers carefully finished.
Phase 3: finishing and handover
During finishing, the roof is fully checked, the last details are finished, the site is cleared and a handover inspection follows together with you. This usually takes 0.5 to 1 day. We take the time to explain which materials were used, what to look out for in terms of maintenance and which guarantee applies. All in all, an average tiled roof project for a family home comes to 3 to 6 working days of physical work, depending on the complexity and extras such as insulation or timber repair.
Want to know how the work proceeds step by step? Then read what replacing a tiled roof involves exactly. If it only concerns loose tiles, the duration is different; see how long roof tile replacement takes.
How we limit the disruption

Working on your roof inevitably brings noise and activity around your home. How the work is organised makes a big difference, though. We work with a tight daily schedule and well-coordinated roofing teams, so there is no unnecessary downtime and no loose ends. Material is delivered in advance as much as possible and placed logically.
Beforehand we make clear agreements on which days and times work will take place, where materials and skips will be placed and how access to your home will be maintained. That way you know when to move your car, what to expect in terms of noise and whether your garden or balcony will temporarily serve as a work area. You have a single point of contact, so questions or changes are dealt with quickly.
- Dust screens where necessary.
- Loose material cleared away every day.
- Old roofing material disposed of safely and separately.
- In rain or strong wind the roof is never left unprotected: we always make it temporarily wind- and watertight.
Cost, lead time and planning
The cost and duration of a tiled roof replacement are closely linked. The more hours needed, the higher the labour costs usually are. In the Netherlands, the average price for completely replacing a tiled roof, including new tiles, battens and standard roofing membrane, is often between approximately €90 and €150 per m². That depends on the type of tile, the condition of the substructure and accessibility. If extra insulation is added at the same time or timber repair is needed, the amount can rise. Read more about how the price is made up in what replacing a tiled roof including roofing membrane costs.
The lead time also determines whether a crane is needed, how many days of scaffolding hire count and how many people work per day. Sometimes it is more favourable to work with a slightly larger team in fewer days; in other situations a smaller crew is more practical. For each project we look at what is most efficient for you, without compromising on quality and safety, and include that in the quote and schedule.
When scheduling, we take into account your diary, holidays, school times and, where possible, the weather. The weather can never be fully predicted, so we always allow some margin for rainy or stormy days, so that your roof is not open longer than necessary. If you combine the replacement with roof insulation, we take that into account in the schedule.
Free roof inspection and personal schedule
A reliable time estimate starts on the roof itself. That is why we offer a free roof inspection as standard, something for which the market often charges between €75 and €200. Our roofer assesses the tiles, battens, roofing membrane, roof decking and the lead and zinc flashing, and identifies hidden defects. You receive a photo report with points of attention and suitable advice.
Based on that, we draw up a personal schedule. It states for each phase how long the work is expected to take, how many days will be spent working on the roof and what preparation is needed. It also states which factors could extend the schedule, such as additional wood rot or extreme weather, and how we deal with them. We agree this schedule with you before the work date is finalised.
Conclusion: a few working days, provided it is well prepared
The duration of a tiled roof replacement depends on much more than the number of square metres. The shape of the roof, the condition of the substructure, the materials and accessibility together determine how many days are needed. For a family home, expect a few working days on average, provided the project is well prepared and no unexpected defects turn up.
As a close-knit family business, we make sure you have clarity about time and cost in advance. We charge no call-out fee and give a 15-year guarantee with certificate on replacing your tiled roof. Want to know how long it will take in your situation? Then book a free roof inspection.
Frequently asked questions about the duration of a tiled roof replacement
How many days does it take to replace a tiled roof?
For a standard house with 60 to 120 m² of roof, the work on the roof usually takes 3 to 5 working days. With finishing and handover, an average project comes to 3 to 6 working days.
How long does the preparation take?
The preparation, with inspection, quote, scheduling and ordering materials, takes 1 to 3 weeks on average. That depends on the delivery time of the tiles and how busy the schedule is.
What can extend the duration?
Wood rot or moisture damage in the roof decking, extra insulation, a complex roof with many dormers and penetrations, a house that is difficult to reach and bad weather can extend the work by one or more days.
Is my roof left open if it rains?
No. In rain or strong wind we always make the roof temporarily wind- and watertight, so it is never left unprotected.
Can I stay at home during the work?
Yes, you can simply stay in your home. We agree in advance when work will take place, where materials will be placed and how access to your home will be maintained.
Do I get a schedule in advance?
Yes. After the free roof inspection you receive a personal schedule per phase, with the expected working days and the factors that could affect the planning.